Pile Driving

Three of our crane barges “VENTURE”,
“DOUBLER” and the “ MICHAEL FINLAY” in Bow Creek.
The works included installation of sheet piles
and riverbank re-build following a partial collapse.
We were in attendance on this contract
for a period of 43 weeks.

|