Construction

The above shows near completion of a hardwood river wall
at Richmond.
The works included the driving of 12 x 12 greenheart piles,
boarding, fendering and the installation of new ground anchors.
The site access was particularly restricted, as this
public park remained open to the general public throughout the works.

|